    1. Year wise Physical & Financial Progress

    Sl/No

    Year

    Physical progress

    Financial Progress

    Remarks

    1

    2018-19

    Nil

    Nil

     

    2

    2019-20

    Nil

    Nil

     

    3

    2020-21

    Nil

    Nil

     

    4

    2021-22

    Nil

    30%

    Works just started

    1. Year wise works details

    Financial Year

    Name of the Model Village

    Works/Activities

    Remarks

    2018-19

    Jurapukhuri

    Nil

     

    Telebasti

    Nil

     

    Buragaon

    Nil

     

    1 No Block 1 No Gaon

    Nil

     

    Niz-Parokhowa

    Nil

     

    Mikirati Howgaon

    Nil

     

    2019-20

    Jurapukhuri

    Nil

     

    Telebasti

    Nil

     

    Buragaon

    Nil

     

    1 No Block 1 No Gaon

    Nil

     

    Niz-Parokhowa

    Nil

     

    Mikirati Howgaon

    Nil

     

    2020-21

    Jurapukhuri

    Nil

     

    Telebasti

    Nil

     

    Buragaon

    Nil

     

    1 No Block 1 No Gaon

    Nil

     

    Niz-Parokhowa

    Nil

     

    Mikirati Howgaon

    Nil

     

    2021-22

    Jurapukhuri

    7 Nos of Schemes

    30 % of the funds released to Construction Committee

    Telebasti

    4 Nos of Schemes

               Buragaon

    6 Nos of Schemes

    1 No Block 1 No Gaon

    11 Nos of Schemes

    Niz-Parokhowa

    12 Nos of Schemes

    Mikirati Howgaon

    16 Nos of Schemes

    AXOM DARXO GRAM YOJANA OF HOJAI DISTRICT

    • * Fund received vide Letter No. PD/DCP/62/2018/PT-II/16 Dated.22/02/2019.

    * District Level Committee was formed on 31/12/2019 vide the Notification No.HJD.22/2018/AAGY/261 Dated.

    * The Village Level Committees were formed vide the Notification No. HJD.22/2018/AAGY 263,264,& 265 Dated.21/01/2021.

    *The district Level meeting on implementation of AAGY was held on 30/07/2021 and all the village level committees were directed to do the following activities:

            1. Survey of the basic facilities of villages.

            2. Prepare list of activities on priority basis with probable date of completion.

            3. Prepare probable cost of the activities.

            4. The District Level Committee Meeting was held on 10/09/2021 where the District Level Committee unanimously approved the village Development Plan Plans submitted by six Village Level Committees and directed to submit Plan & Estimates of the approved Schemes. After the submission of the Schemes , fund has been sanctioned to the Construction Committees on 30/10/2021.

            5. Due to shortage of Officers & Staff in the District Planning Cell, Timely implementation of the schemes are being hampered.

    Downloads
    TitleSizeDetail
    Year Wise Physical & Financial Progress of Axom Adarxo Gram Yojana for the Year-2021-2244.15 KBswf-image
    Village Wise Works Axom Adarxo Gram Yojana86.05 KBswf-image
    Burhagaon Model Village Village Dev Plan1.75 MBswf-image
    Niz Parakhowa Model Village Village Dev Plan1.81 MBswf-image
    Mikirati Haogaon Model Village Village Dev Plan1.89 MBswf-image
    Jurapukhuri Model Village Village Development Plan1.62 MBswf-image
    1No Block 1No Gaon Model Vilkage Village Dev Plan645.63 KBswf-image
    Telebasti Model Village village dev plan895.76 KBswf-image
    Minutes of the District Level Committee, Axon Adarxo Gram Yojana416.07 KBswf-image